ID WBS Task Name Duration Start Finish Predecessors Cost 1 1 PROJECT X 380 days 01-11-2022 15-04-2024 £514,880.00 2 1.1 Project Start 0 days 01-11-2022 01-11-2022 £0.00 3 1.2 Activity A 147 days 01-11-2022 24-05-2023 £175,280.00 4 1.2.1 A1 10 days 01-11-2022 14-11-2022 2 £13,600.00 5 1.2.2 A2 9 days 15-11-2022 25-11-2022 4 £10,800.00 6 1.2.3 A3 23 days 23-11-2022 23-12-2022 5FS-3 days £14,720.00 7 1.2.4 A4 21 days 14-12-2022 11-01-2023 £24,880.00 8 1.2.4.1 A4a 13 days 14-12-2022 30-12-2022 6FS-8 days £11,440.00 9 1.2.4.2 A4b 7 days 03-01-2023 11-01-2023 8FS+1 day £13,440.00 10 1.2.5 A5 29 days 12-01-2023 21-02-2023 £31,280.00 11 1.2.5.1 A5a 24 days 12-01-2023 14-02-2023 9 £26,880.00 12 1.2.5.2 A5b 5 days 15-02-2023 21-02-2023 11FS-1 day £4,400.00 13 1.2.6 A6 26 days 22-02-2023 29-03-2023 £31,920.00 14 1.2.6.1 A6a 15 days 22-02-2023 14-03-2023 12 £22,800.00 15 1.2.6.2 A6b 6 days 22-03-2023 29-03-2023 14FS+5 days £9,120.00 16 1.2.7 A7 40 days 30-03-2023 24-05-2023 £48,080.00 17 1.2.7.1 A7a 20 days 30-03-2023 26-04-2023 15 £30,400.00 18 1.2.7.2 A7b 17 days 02-05-2023 24-05-2023 17FS+3 days £17,680.00 19 1.3 Activity B 233 days 25-05-2023 15-04-2024 £339,600.00 20 1.3.1 B1 176 days 25-05-2023 25-01-2024 £64,800.00 21 1.3.1.1 B1a 17 days 04-10-2023 26-10-2023 22FS+6 days £31,280.00 22 1.3.1.2 B1b 11 days 25-05-2023 08-06-2023 18 £11,440.00 23 1.3.1.3 B1c 23 days 26-12-2023 25-01-2024 33,34 £22,080.00 24 1.3.2 B2 180 days 09-06-2023 15-02-2024 £83,760.00 25 1.3.2.1 B2a 28 days 27-10-2023 05-12-2023 21FS-4 days,26 £47,040.00 26 1.3.2.2 B2b 21 days 09-06-2023 07-07-2023 22 £15,120.00 27 1.3.2.3 B2c 15 days 26-01-2024 15-02-2024 23 £21,600.00 28 1.3.3 B3 180 days 10-07-2023 15-03-2024 £75,360.00 29 1.3.3.1 B3a 12 days 08-12-2023 25-12-2023 25FS+2 days,30 £23,040.00 30 1.3.3.2 B3b 13 days 10-07-2023 26-07-2023 26 £24,960.00 31 1.3.3.3 B3c 19 days 20-02-2024 15-03-2024 27FS+2 days £27,360.00 32 1.3.4 B4 188 days 27-07-2023 15-04-2024 £115,680.00 33 1.3.4.1 B4a 37 days 14-08-2023 03-10-2023 34 £71,040.00 34 1.3.4.2 B4b 12 days 27-07-2023 11-08-2023 30 £23,040.00 35 1.3.4.3 B4c 15 days 18-03-2024 05-04-2024 31 £21,600.00 36 1.3.4.4 Project Completion 0 days 15-04-2024 15-04-2024 35FS+6 days £0.00 01-11 Equipment[3],Skilled labour[2],Unskilled labour[3] Equipment[2],Skilled labour[2],Unskilled labour[3] Equipment,Skilled labour,Unskilled labour[4] Equipment,Skilled labour[2],Unskilled labour[2] Equipment[3],Skilled labour[3],Unskilled labour[3] Equipment,Skilled labour[3],Unskilled labour[3] Equipment,Skilled labour[2],Unskilled labour[2] Equipment[2],Skilled labour[3],Unskilled labour[3] Equipment[2],Skilled labour[3],Unskilled labour[3] Equipment[2],Skilled labour[3],Unskilled labour[3] Equipment[2],Skilled labour,Unskilled labour Equipment[4],Skilled labour,Unskilled labour Equipment[2],Skilled labour,Unskilled labour Equipment[2],Unskilled labour[2] Equipment[3],Skilled labour[2],Unskilled labour[2] Equipment,Skilled labour,Unskilled labour[2] Equipment[3],Unskilled labour[3] Equipment[3],Skilled labour[4],Unskilled labour Equipment[3],Skilled labour[3],Unskilled labour[3] Equipment[3],Unskilled labour[3] Skilled labour[3],Unskilled labour[3],Equipment[3] Skilled labour[3],Unskilled labour[3],Equipment[3] Equipment[3],Unskilled labour[3] 15-04 16-10 23-10 30-10 06-11 13-11 20-11 27-11 04-12 11-12 18-12 25-12 01-01 08-01 15-01 22-01 29-01 05-02 12-02 19-02 26-02 05-03 12-03 19-03 26-03 02-04 09-04 16-04 23-04 30-04 07-05 14-05 21-05 28-05 04-06 11-06 18-06 25-06 02-07 09-07 16-07 23-07 30-07 06-08 13-08 20-08 27-08 03-09 10-09 17-09 24-09 01-10 08-10 15-10 22-10 29-10 05-11 12-11 19-11 26-11 03-12 10-12 17-12 24-12 31-12 07-01 14-01 21-01 28-01 04-02 11-02 18-02 25-02 03-03 10-03 17-03 24-03 31-03 07-04 14-04 21-04 28-04 05-05 12-05 19-05 26-05 02-06 09-06 16-06 November December January February March April May June July August September October November December January February March April May June Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: Project1 Date: 03-05-2022